Eisenerz-Developer Black Iron legt attraktives BFS-Update vor

Zwar sind die 1+ Bn CAPEX-Projekte im Minen-Sekor bei dieser Marktlage natürlich weiterhin de facto uninteressant, jedoch ist das Black Iron (T.BKI) Projekt long term ein fast sicherer 'no brainer'. Wären da nicht die heftigen Instabilitäten in der Ukraine..

Black Iron Updates Bankable Feasibility Study Showing 48% IRR, 2 Year Payback and US$3.3 Billion NPV for Shymanivske Project
TORONTO, ONTARIO--(Marketwired - Jan. 23, 2014) - Black Iron Inc. ("Black Iron" or the "Company") (TSX:BKI) (FRANKFURT:BIN) has updated its current Bankable Feasibility Study ("BFS"), incorporating pilot plant test work, completed on its Shymanivske Iron Ore Project located in Krivoy Rog, Ukraine (the "Project"). The updated BFS outlines an operation producing 9.9 million tonnes per year of high-grade 68% iron ore concentrate, projecting a 48% internal rate of return ("IRR"), two year payback and a US$3.3 billion net present value ("NPV") at an 8% discount rate..
Feasibility study outlines an operation producing 9.9 million tonnes per year of high-grade 68% iron ore concentrate, projecting a 48% IRR, 2 year payback and a US$3.3 billion NPV at an 8% discount rat
Changing to wet cobbing at a finer particle size results in an increase from 10% to 40% rejection of waste rock prior to grinding and elimination of the second grinding stage resulting in a 14% reduction in total operational running power 
Reduction of plant footprint through a more optimal layout and an 8% increase in iron ore concentrate production from 9.2 to 9.9 million tonnes per year with essentially no change in capital cost..
..
Link: http://www.marketwired.com/press-release/black-iron-updates-bankable-feasibility-study-showing-48-irr-2-year-payback-us33-billion-tsx-bki-1871714.htm